Important – North Parking Lot Replacement – June 20th

Hello Challenger Park Residents,

The Board of Directors is pleased to announce that we will begin resurfacing the parking lots in the Northern quads beginning on June 20th. Parking lot access to the Northwest and Northeast quads will be limited on 6/20 & 6/21 during the day. There will be no traffic allowed to the Northern Parking lots 6/22-6/23 during paving, to avoid any issues with vehicle access, we are asking residents of the Northern quads to park either along Wintergreen or in the Southeast Christian Church parking lot between 6/20-6/23. Southeast Christian Church approved our residents to use their parking lot on weekdays only while we are doing construction. Below are the estimated dates for the asphalt resurfacing activities. Weather could delay expected construction activities.

June 20th: milling starting at 8 am East side first, then West side parking lot will be open to drive on in the evening after 6pm

June 21st: patching starting on the East side then moving to the West side. Parking lot will be open in the evening after 7pm

June 22nd: paving East side starting at 8am no traffic until next day

June 23rd: paving West side starting at 8am no traffic until next day

Apologies for any inconveniences caused by the road construction.

Sincerely,

Your Challenger Park Board of Directors